Project Objectives
Fortify people-oriented and gender-responsiveurban governance and concomitant service delivery in the Projectpourashavas of the country Develop these target pourashavas in a holistic and integrated manner in relation to governance and infrastructure explicitly featured by well-developed municipal service delivery, citizen participation, financial sustainability, transparency, accountability, inclusiveness and planned urban development.
Develop these target pourashavas in a holistic and integrated manner in relation to governance and infrastructure explicitly featured by well-developed municipal service delivery, citizen participation, financial sustainability, transparency, accountability, inclusiveness and planned urban development.
Project Background
Mainstream: Governance Improvement of Project Municipalities Capacity Development of Project Municipalities Operation and Maintenance of Infrastructure and Waste Management Infrastructure Development Roads Drains Municipal Facilities Improvement of Disadvantaged Area
Main stream 63 Pourashava, Chittagong Division(19 nos )- Brahmanbaria, Sonagazi, Haziganj, Matlab, Faridganj, Raipur, Ramgati, Ramganj, Chowmuhoni, Chandanaish, Sandwip, Bhanskhali, Raozan, Nazirhat, Bandarban,Khagrachhari,Basurhat,Rangamati,Daganbhuiyan; Dhaka Division(17 Nos): Madhupur, Kaliganj, Kaliakair, Monohardi, Munshiganj, Mirkadim, Araihazar, Goalanda, Bhanga, Boalmari, Kalkini, Naria, Hossainpur, Pakundia, Bhairab, Manikganj, Tungipara; Rangpur Division(03 Nos): Patgram, Ulipur, Sundarganj; Rajshahi Division(10 Nos): Santhia, Rohanpur, Shibganj, Charghat,Bagha, Naohata, Bhabanigonj, Keshorehat, Nazipur, Sariakandi; Mymenshing(03 Nos): Madan, Nokla, Gaforgaon; Khulna Division(07 Nos): Bheramara, Kumarkhali, Gangni,Alamdanga,Keshabpur, Monirampur, Mahespur;
Sylhet Division(04 Nos): Kulaura, Chunarughat, Chhatak, Moulvibazar;
Operation and Maintenance- 25 Pourashava, Dhaka Division(03 Nos) : Gopalganj, Kishoreganj, Rajbari; Khulna Division (05 Nos) : Meherpur, Chuadanga, Benapole, Jashore, Magura, Rajshahi Division (06 Nos): Chapai Nawabgonj, Joypurhat, Naogaon, Bera, Ishwardi, Shahjadpur Chittagong Division (03 Nos) : Nabinagar, Laksam, Laxmipur Mymenshing Division (03 Nos): Muktagacha, Netrakona, Sherpur Barisal Division (02 Nos): Barguna, Pirojpur Rangpur Division (03 Nos): Lalmonirhat, Nilphamari, Panchagarh
Source of Fund : a) ADB: (US$ 300 million & Grant amount US$ 2.00 million for Technical Assistance= US$ 302 million ) b) AFD : (US$ 200.00 million) c) GOB : (US$ 100.00 million)
Implementation Period : Start date: 01 July 2023 Completion Date: 30 June 2028
Date of approval by the ECNEC/ Planning Commission/Ministry : ECNEC Meeting Approval Date : 20.06.2023 ECNEC GO Date : 17.07.2023 LG Ministry's Administrative order issue Date: 25.07.2023 Loan Signing ADB: 14.08.23 Loan Negotiation AFD : 11.09.2023 Loan Effective : 12.10.2023
Physical Target : To achieve planned, inclusive and sustainable urbanization, better city governance, and improved infrastructure and service provisions. • At least 900 km of drainage rehabilitated or constructed in 63 target Pourashavas. • At least 1,500 km of roads rehabilitated or constructed to meet standards of gender¬ responsiveness, safety, and accessibility in target pourashavas. • At least 7 communityfacilities, including climate resilient and inclusive public space, remodeled or developed. Impoverished settlement (impoverished enclaves) improvement Project implemented with at least 50% women participation in all 63 pourashavas